CHIEF OF STAFF AND HEAD OF PUBLIC SERVICE INSPECTS PROGRESS AT GALANA KULALU FOOD SECURITY PROJECT, COMMISSIONS 1MW SOLAR POWER PLANT – 3RD NOVEMBER 2026
Later the team visited Galana Kulalu Food Security Project in Kilifi and Tana River Counties to inspect the remarkable progress made in revitalising the Project by the National Irrigation Authority through strategic partnership with private investors.
Following years of infrastructure development, the impact of the project is being realised and more is set to come with progressive increment in area under irrigation.
Currently, approximately 2,000 acres is under seed maize while an additional 2,000 acres is targeted to be put under Soya Beans and 2,000 acres under commercial maize. Cropping will be increased progressively to 20,000 acres using the available water resources and installed irrigation infrastructure.
During the visit, the Chief of Staff and Head of the Public Service commissioned a 1MW solar power plant installed by the investors to provide clean and affordable energy to support irrigation pumping operations and packhouse activities.
The delegation also inspected the Galana Kulalu Water Reservoir, with a storage capacity of 450,000 cubic metres. The reservoir draws water from the Galana River and serves as a desilting basin, minimising sediment accumulation and reducing wear and tear on irrigation infrastructure while ensuring a reliable water supply for agricultural production across two cropping seasons annually.
To further strengthen water security and support the project’s long-term expansion, the Authority is advancing plans for the construction of the 305 million cubic metre Athi Dam upstream. The dam is expected to provide a sustainable, year-round water supply to support irrigation across up to 300,000 acres. The National Irrigation Authority has already signed the contract for the project, with preparations for its launch at an advanced stage.
The tour further included an inspection of the newly constructed 200-metre Galana Kulalu Bridge across the Galana River. The bridge provides a direct connection between Kilifi and Tana River counties to the Malindi-Sala Gate Road, significantly improving accessibility and easing the transportation of agricultural inputs, produce and other essential commodities to markets.
The progress at Galana Kulalu demonstrates the transformative impact of irrigation development, strategic public-private partnerships and sustained investment in agricultural infrastructure. Through the project, the National Irrigation Authority remains committed to unlocking the country’s agricultural potential, expanding irrigated land, creating employment opportunities, particularly and advancing the national food security agenda as espoused in the Bottom-Up Economic Transformation Agenda (BETA).